Pahang Selangor Raw Water Tunnel

Trio of TBMs bore Malaysia’s Largest Infrastructure Project

Machine Type Main Beam TBM
Diameter 3 x 5.23 m (17.2 ft)
Tunnel Type Water Transfer
Tunnel Lengths 11.77 km (7.31 mi), 11.80 km (7.33 mi), 11.30 km (7.02 mi)
Owner Malaysian Ministry of Energy, Green Technology, and Water (KeTTHA)
Contractor SNUI JV (Shimizu Corporation, Nishimatsu Construction, IJM Construction Sdn Bhd, UEM Builders Bhd)
Location Pahang and Selangor States, Malaysia

Project Overview

First of three Robbins machines being launched from an aditThe Pahang Selangor Raw Water Tunnel, for the Malaysian Ministry of Energy, Green Technology, and Water, will convey raw water from the Semantan River in Pahang to the South Klang Valley area of Selangor state. The three tunnels, totaling 44.6 km (27.7 mi), will address projected water shortages due to the area’s rapidly growing population. Once completed, the tunnel will transfer 27.6 cubic meters (7,300 gallons) of water per second to a new treatment plant. The drinking water will supply about 7.2 million people by 2013.

The SNUI JV, consisting of Shimizu Corporation, Nishimatsu Construction, UEM Builders Bhd, and IJM Construction, chose three Robbins 5.23 m (17.2 ft) diameter Main Beam TBMs to excavate the three sections of the tunnel. The total supply includes back-up systems, continuous conveyors, cutters, spares, and field service personnel.

Ground Support and TBM Design

Tunneling is taking place in the high cover conditions, up to 1,200 m (3,900 ft) below the Titiwangsa mountain range. Geology during the initial stages of advance consists of hard, abrasive granitic rock up to 200 Mpa (29,000 psi) UCS. The tunnels are being supported with ring beams, rock bolts, and shotcrete depending on the conditions. If unstable ground is encountered, invert thrust systems can be utilized to avoid gripping against the tunnel walls.

To successfully excavate the hard rock, each High Performance (HP) TBM has been fitted with 19-inch (482 mm) back-loading disc cutters- making them the smallest diameter back-loading cutterheads ever provided. The cutters are being carefully monitored for wear using remote monitoring systems. The wireless systems allow the crew to plan cutter changes and keep track of wear by recording several variables on each cutter, including cutter rotation (which is computed to percentage wear), temperature, and vibration.  Each 19-inch face and gage cutter is equipped with a sensor bolted inside the cutter housing, allowing raw data to be sent to a program display in the operator’s cabin.

Tunnel Excavation

TBM breakthrough in Malaysia, March 2013.The first machine was launched on November 10, 2010, followed shortly after by the second on December 30, 2010. The third machine began boring in March 2011 and all three machines are currently boring as scheduled. All of the machines were assembled outside their particular adits, then “walked” down a 6-10% grade to an NATM-excavated starter tunnel. Two of the machines were launched with a shortened back-up configuration of 10 decks and a temporary transfer conveyor, while the third for logistical reasons utilized trucks for muck removal in the preliminary boring phase. Once the machines had advanced about 100 m (330 ft), the remaining back-up decks and permanent Robbins continuous conveyor were then installed, due to the adit configurations.

During the initial stages of advance, the machines achieved rates of up to 3.5 m (11.5 ft) per hour, leading the three machines to excavate over 1,400m (4,600 ft), 540 m (1,800 ft) and 330 m (1,100 ft), respectively by April 2011.  As each TBM continued on its 11km (6.8 mi) run, the machinery had to overcome adversity including blocky rock, over-break, power outages and water inflows.  The collaboration of Robbins field service and joint venture contractors, Shimizu Corporation, Nishimatsu Construction, UEM Builders, and IJM Construction (SNUI) allowed the TBMs to maintain strong advance rates of 475m (1,560 ft) on average per month, and up to 650 m (2.130 ft) per month.

Among other methods of ground support used during boring, the near-zero rebound fiber mortar (sprayed shotcrete) is the primary method being used during the Pahang Selangor Project.  This marks the first time this method has been used outside of Japan.  The success of this innovative implementation has been proven through reduced project downtime, dust reduction and good bonding.

Breakthrough

The first of three 5.23 m (17.2 ft) Main Beam Robbins TBMs broke through at the Pahang Selangor Raw Water Tunnel on March 22, 2013 to a large ceremony of cheering onlookers. The breakthrough was attended by dignitaries, contractors and honored guests, with everyone very enthusiastic about the machine’s success.  It was a moment worthy of celebration; the breakthrough is a significant step towards the completion of the longest tunnel in Southeast Asia.

The breakthroughs for the two remaining 5.23 m (17.2 ft) machines are on schedule, with each boring a respective 11 km (6.8 mi) and expected to meet inside the tunnel by autumn 2013.

Updates of this project will be posted as boring continues.